Service Guide
EK-HSG80-UP. B01 Page 3
Table 1–1 Number of HSZ70 SCSI Logical Units vs. HSG80 Fibre Channel
Logical Units – Cont.
Connection Type
Operating System
SCSI Logical Units
Fibre Channel Logical Units
WNT - Intel 8 TIDs X 8 LUNs = 64 LUNs 2 ALPAs X 8 LUNs =16 LUNs
Tru64 Unix 8 TIDs X 8 LUNs = 64 LUNs 2 ALPAs X 8 LUNs = 16 LUNs
IBM AIX 8 TIDs X 8 LUNs = 64 LUNs 2 ALPAs X 16 LUNs = 32 LUNs
2.0 Upgrade Roadmap
Table 2-1 below outlines the specific tasks and actions involved in the upgrade process. Its
purpose is to give you an overview and process flow for following the necessary steps in
upgrading an HSZ70 to an HSG80 Array Controller.
Table 2–1 Roadmap
Task Action
Reference
1
Hardware Inventory
Determine if all of the
necessary hardware and
software components are
available.
⇒ Section 3.0, Hardware Inventory
2
Prepare the Server
Backup the user data and
host configuration.
⇒ Section 4.0, Preparing the
Server
3
Prepare the Client
Save the HSZ70
configuration and uninstall
StorageWorks Command
Console (SWCC) if using
SWCC.
⇒ Section 5.0, Preparing the
Client
4
Remove Server
Components
Uninstall the SWCC Agent,
and remove the SCSI Host
Adapter(s).
⇒ Section 6.0, Removing the
Server Components
5
Prepare HSZ70
Record the storageset and
unit configuration, then
shutdown the HSZ70
controller(s).
⇒ Section 7.0, Preparing the
HSZ70
6
Remove HSZ70
Components
Disconnect all cables and
remove all of the necessary
hardware.
⇒ Section 8.0, Removing the
HSZ70 Components